| Case Study
CHALLENGE: Replace large 480-volt switchgear for a major food manufacturer.
SOLUTION: Instead of an expensive total replacement, the Wunderlich-Malec team identified an option for a cost-effective retrofit. We selected a suitable vendor, developed a detailed, phased construction plan, and managed a multi-discipline contractor install.
RESULT: The retrofit resulted in a 35% cost savings and a substantial reduction in implementation time. |